Project Name: Project Management of 50 MV Merchant Gas Fired Power Station and 132 kV Switchyard.
Customer: ENERGY PRIMA LIMITED
Application: Power Station
Rating: 50 MV & 132kV Switchyard
Consultant: EPC International Pty Ltd
Completion Year: November 2008



ENERGY PRIMA LIMITED
About EPC
Project Name: Design ,Project Management and training Aitutaki-Power Station - Cooks Island
Customer: Cummins South Pacific
Application: Power station
Rating: High Voltage 11kV & 3.3kV Switch Board
Consultant: EPC International Pty Ltd
Completion Year: September 2009
Cummins South Pacific

 

Project Description

......... Customer ........ $A ....... Year

Design, Document, Construct, Certify Three Story Library Building for University of Fiji.


University of Fiji Limited


1,200,000


June 2010- Under Execution


Design, Supply, Install, Test and Commission of Lighting and Power in BRES 57-62, Hilton Resort -Fiji.


Hilton Resort -Fiji


900,000


Feb 2010


Turnkey Upgrade of 11kV Nadi Power Station Switchgear with 10 nos of New Panels with Bustlie and Related Protection and Scada Upgrade with All Civil and Site Works.


Fiji Electricity Authority


600,000


Nov 2009


11kV Natadola Marine Resort HV Reticulation - Turnkey Design, Manufacture, Supply, Install, Test and Commission 11kV Power Cabling , 11kV / 415V Kiosks with All Treching , Backfilling Civil and Site Works Including 11kV 1.2MVAr Swithched Cap Banks Natadola Marine Resort Limited 1,500,000 May 2009

Project Management of 50 MV Merchant Gas Fired Power Station and 132kV Switchyard and Auxiliary Plant in Bangladesh Energy Prima Limited 250,000 Nov 2008

Design, Document , Specify 33kV & 11kV Reticulation Power System with Cable and Pad Mount Easements.33/11kV Natadola Marine Resort HV Reticulation - Consultancy Natadola Marine Resort Limited 200,000 May2008

Design, Supply, Install, Test and Commission- 10 Units of 100kV ar Switched Capacitor Banks for Raki-Raki & Korovou Power Stations Fiji Electricity Authority 200,000 April 2008

Turnkey Design , Manufacture , Supply , Install, Test and Commission 33kV with Related Protection and Scada for Sigatoka Sub station with All Civil and Site works Including 1.2MVAr, 33kV Switched Capacitor Banks Fiji Electricity Authority 980,000 April 2008

Turnkey Design, Manufacture, Supply, Install, Test and Commission 11kV / 145V Power Cabling, 11kV /415V Kiosks, with All Trenching, Backfilling Civil and Site Works. -Laucala Bay Resprt HV & LV Reticulation Rawlinsons- Suva JV with Sigatoka Electric 1,000,000 Dec 2007

Turnkey Design , Manufacture, Supply , Install , Test and Commossion 33kV with Related Protection and Scada for Nscocolevu Switching Station with All Civil and site Works Fiji Electricity Authority 800,000 Dec 2006

Turnkey Design, Manufacture, Supply , Instal, Test and Commission 415V with Related Protection and Scada for Kinoya Power Station. Fiji Electricity Authority 300,000 June 2005

Turnkey Upgrade of 11kV Power Station Switchgear with 8 Nos of New Panels with Bustile and Related Protection and Scada Updrade with All Civil and site Works- Sigatoka Power Station Upgrade Fiji Electricity Authority 500,000 Mar 2005

Installation of 300 kVA 33/11 kV Zig-Zig Earthing & Auxiliary Transformers for Sigatoka -Fiji Fiji Electricity Authority 60,000 Mar 2005

Installation of 20/27 MVA 66/11-6.6. KV Dyn1 Power Transformers for Sub-c Brunswick City Power 1,200,000 Feb 2005

Turnkey Design , Manufacture, Supply , Install, Test and Commission 33kV with Related Protection and Scada for Sabeto Switching Station with All civil and Site works. Fiji electricity Authority 750,000 Dec 2004

Turnkey Upgrade 33kV Switchyard Bay with Transformer Refurbishing Circuit Breaker, Disconnector, Surge Arrester , 33 /11 kV Cabling and three nos 11kV Panels with Bus Tie Complete with All Site Works, Wailekutu Sub Station Upgrade Fiji Electricity Authority 500,000 Sept 2004

Turnkey Upgrade of 11kV Kinoya Power Station Switchgear with 9 Nos of New Panels with Bustle and Related Protection and Scada Upgrade with all Site Works
Fiji Electricity Authority 250,000 Aug 2004

Design ,Supply, Installation & Pre-Test 362kV HV Disconnector At Sydeny West for Transgrid Transgrid -NSW 10,000 Mar 2004

Turnkey Upgrade of 132kV System with Transformers Supply, 33kV Switchgear Panel and Related Protection, Control with All Site works - Wailoa Substation Upgrade Fiji Electricity Authority 700,000 Feb 2004

Installation of 300 kVA 33 /415 kV Dyn1 Auxiliary - Transformer for Sabeto Turnkey Project -Fiji

Fiji Electricity Authority
20,000 Dec 2004

Installation of 10/12.5 MVA 132/33kV Dyn1 Power Transformer for Wailoa Turnkey Project Fiji Electricity Authority 150,000 Nov 2003

Actew ~ Installation & Commissioning of 11kV Switchboard Substation at Fyshwick HSS 24,000 2001

Cronulla ~ Installation & Commissioing ; 11kV Substation at Cronulla Stp. HSS 25,000 2001

Design , Supply , Installation of Electrical & Instrument Upgrade works at Whittlesea Stp Victoria.

Houlton Construction / Yarra Valley Water 180,000 2001

Mornington STP Victoria Complete Electr Instrumentation Upgrade ( Engineering Services & Project Management) Houlton Construction / Yarra Valley Water 20,000 2001

Power Quality Investigation of TNBD Network for Banting , Westport , Bukit Raja & Shah Alam Areas and Provide Solution With CD Elect SDN.BHD .Mr Reinhausen Germany 200,000 2001

Design Services Consulting Brain Storm HYDRO TAS,TRANS; ENGG 2,000 2001

Consulting Services for 33k V Upgrade Cabling Tender Preparation in Malaysia CW Elect/ HG Power SDN BHD 5,000 2001

220/66 kV Shunt CapBanks Tender Consulting Agility 4,000 2001

Investingation of Network Harmonics and Design and Supply of 11kV Pole Top Capacitor Banks for Fiji Electricity Authority Fiji Electricity Authority 40,000 2002

Installation of Electrical & Instrumentation works , Hastings STP Victoria Lagoon- 2 Elect Thames Water 100,000 2000

Consulting , 330 kV Cable Termination Design Power Link / Jabatous Aust 5,000 2000

Sales Consulting for large Substation Tenders National Power Services 10,000 2000

110/11 kV Risdon Substation Tender Consulting Powercor
5,000 2000

Project Mangement and Design Assigment -11 kV Switchboard Cronulla STP HSS 10,000 2000

Design , Supply , Instal & Test Pumping Station Electrics & Instrumentation - Rennison Road Westen Port Water 15,000 1999

Design and Supply , Commission Diesel Gen Set Auto Changeover Controls Beachcomber & Norseman sps Westen Port Water
12,000 1999

Baotau Laddle Furnace - Design , Supply & Instal Supervision of -35kV Harmonic Filter bank- China Mr. Reinhausen / Germany 120,000 1999

Design , Project Managment & Electrical Installation & Comission for 11kV Switch Board at Kinoya Fiji Ekectricity Authority / HSS 60,000 1999

Zinc Smelter - Supply of 35kV Post Insulators from Lapp USA Mr . Reinhausen 25,000 1999

Design , Supply Civil wroks , Instal & Test Switchyard Mate Zinc Smelter- 35 kV Ripple Frequency Blocking Filter Mr . Reinhausen 300,000 1999

Indirect Project Sales Reference List Under Agency Agreement

Project Description Customer $A Year

Sales Consulting - Acquistion of Projects with State of The Art Hybrid Tech. and Sales of Other Substation Projects Siemens Ltd 200,000 1999

MV Switchgear Order for HSS for Bolivar Pump STN under Agency Agreement with HSS. HSS/ AMEC- SA 600,000 1999

22 kV Reclosers Sale to AGL Victoria - Under Agency Agreement with HSS. HSS/ AGL 800,000

11 KV Switchgear Order for Arthors Lake HSS/ HYDRO Tasmania 100,000 Completed

11KV Switchgear Order for SA Water HSS/ SA Water 350,000 Completed

33KV Horizon Circuit Breakers Ordered By Powercor - 02/Powercor/ 005 HSS/ SA Water 400,000 Completed

33KV Horizon Circuit Breakers Ordered By Powercor - 02/ETSA/ 006 HSS/ SA Water 400,000 Completed

22 KV Reclosers Sale to AGL Victoria HSS/ AGL 400,000 Completed